Transport infrastructure projects in Ho Chi Minh City are delayed due to obstacles in relocating utility poles
In the process of expanding and upgrading transport infrastructure, several key projects in Ho Chi Minh City are facing major challenges related to the relocation of utility poles, causing delays and posing various traffic safety risks. Projects such as the expansion of Tan Thuan Thien Quy Road, Duong Quang Ham Road, and Ba Ham Bridge have encountered difficulties related to the untimely removal and undergrounding of the power system. These obstacles not only affect construction progress but also create complex traffic management issues and threaten the safety of residents traveling through the construction areas.
The expansion project of Tan Thuan Thien Quy Road commenced in March 2023 with a total investment of over 120 billion VND and is expected to be completed in October this year, aiming to reduce congestion at the southwestern gateway of Ho Chi Minh City. This road is crucial for connecting Tan Son Nhat Airport and surrounding areas, so completing it on time is extremely important for improving transport infrastructure and enhancing residents' quality of life. However, dozens of utility poles have not yet been relocated and remain in the middle of the road, becoming dangerous obstacles for road users. Many residents report having to weave between the poles, especially at night when visibility is limited, increasing the risk of accidents. This situation not only causes inconvenience but also affects community safety, particularly during adverse weather conditions or peak traffic hours.
The upgrade project of Duong Quang Ham Road, which restarted in late 2023, faces a similar situation. Hundreds of utility poles have not yet been removed and remain in the middle of the road, while vehicles continue to pass through, creating a chaotic scene and a high risk of collisions. The cables are tangled intricately and sometimes sag to lower positions, further increasing the danger to pedestrians. In particular, these cables not only hinder the passage of vehicles but also pose a threat to children and the elderly in the area. The transport infrastructure in this area greatly needs to focus on safety, as this is a main road connecting many densely populated residential areas and commercial activities.
One of the main reasons for the delay in relocating utility poles is the need to synchronize the undergrounding of the power system with the road construction progress. This process requires the installation of sewers and technical manholes before the power department can begin pulling cables and removing old poles. This requires complex and precise coordination among multiple parties, including construction contractors and infrastructure management units. However, the process is time-consuming and affected by difficulties in demolition and other technical issues, leading to project delays. Many residents disagree with changes to the locations of utility poles or substations, causing delays in land handover, which directly affects the construction schedules of the power department and contractors.
The Ho Chi Minh City government and relevant parties are actively cooperating to resolve this situation. Ho Chi Minh City Power Company has committed to accelerating the undergrounding progress and removing utility poles to ensure traffic safety. For the Tan Thuan Thien Quy Road and Ba Ham Bridge projects, the poles are expected to be removed by mid-November this year. Meanwhile, on Duong Quang Ham Road, undergrounding construction is expected to be completed by mid-2025, which requires importing sufficient equipment from abroad. Part of the reason for these delays is that control equipment and key materials need to be imported from abroad, requiring lengthy bidding and transportation processes. This poses considerable challenges for project management units in ensuring construction progress and controlling engineering quality.
The delay in relocating utility poles not only affects project completion schedules but also brings potential risks of traffic accidents. Poles located in the middle of the road cause considerable inconvenience and risk to residents. The government and construction units need to strengthen coordination, set up warning signs, and hang reflective ropes to alert road users and ensure safety during construction. Additionally, all parties need to continuously inspect and clear construction debris and other materials to keep the road clear, reducing risks to road users, especially at night or during peak traffic periods.
These efforts will help Ho Chi Minh City improve its transportation infrastructure, reduce congestion, and ensure safe passage for residents on roads undergoing upgrades. Enhancing the quality of infrastructure not only helps improve residents' quality of life but is also a key factor in driving the city's economic and social development. Convenient transportation infrastructure will create conditions for commercial and service activities, attract more investors to the area, and thereby promote economic growth. The government and relevant units need to formulate long-term strategies to ensure the synchronized and sustainable development of transportation infrastructure, while also improving management and supervision efficiency to avoid the recurrence of current progress delays.
In addition, the implementation of the project requires detailed planning and careful calculation of various technical and social factors, from land acquisition and relocation to the management of human resources and materials. Flexible solutions are needed to minimize the impact of the construction process on residents' daily lives, especially for families living and doing business near the site. Only when all parties maintain close cooperation and continuous effort can Ho Chi Minh City achieve its goal of improving and upgrading transportation infrastructure, moving toward a modern, convenient, and safe city that provides a better living environment for everyone.
#FTT Real Estate Co., Ltd.
(#Real Estate Consulting / #Leasing and Property Management and Sales / #Furniture and Decoration)
LINE official account @ymq0321f|Zalo +886 956 918 888|WeChat
┃Youtube: FTT REAL ESTATE
┃Website : www.fttland.com