Admiring the 'heart' of Long Thanh Airport after nearly 300 days of construction
Admiring the 'heart' of Long Thanh Airport after nearly 300 days of construction
After nearly 300 days of construction, the passenger terminal of the Long Thanh Airport Phase 1 project—the 'heart' of the airport—has begun to take shape. This building, inspired by the lotus flower, is currently 10-20 days ahead of the contractual schedule.
Lotus-shaped passenger terminal takes shape
The passenger terminal (Package 5.10, part of the third section of Long Thanh Airport Phase 1) began construction in late August 2023. The total investment for this project exceeds 3,500 billion VND, and upon completion, it will be able to handle 25 million passengers and 1.2 million tons of cargo annually.
According to the Airports Corporation of Vietnam (ACV), the passenger terminal includes a central building and three wings, with a structure of one ground floor and three upper floors, and a roof height of 45.55 meters. The building is designed with separate departure and arrival levels, with a total floor area of approximately 376,451 square meters, and 40 aircraft parking positions capable of accommodating Code C, E, and F aircraft.
Original image: cdn.tuoitre.vn
Construction progress ahead of schedule
Currently, the construction consortium has deployed about 3,300 workers and 950 pieces of equipment on site. To ensure construction progress, ACV has required the consortium to overcome difficulties and organize shift work in a 'three shifts, four rotations' pattern.
As of May 22, the passenger terminal has basically completed the reinforced concrete work for all columns on the first floor, and the concrete beam and slab construction area on the first floor has reached 97,200 square meters, accounting for 85% of the total area of 114,000 square meters. ACV's report indicates that by the end of May 2024, the contractor is expected to complete 100% of the concrete beam and slab structure on the first floor, which is about 20 days ahead of the contractual schedule, with the overall progress also being 10 days ahead.
Other related works
Alongside the passenger terminal, Package 4.6 also started construction, which includes the runway (dimensions 4000x45 meters), taxiways, rapid exit taxiways (total area of about 69.3 hectares), 20 aircraft parking positions (area of about 47.09 hectares), and an apron for ground service vehicles (area of about 12.4 hectares).
Since the start of construction, the consortium has mobilized 1,500 personnel and 350 pieces of equipment, setting up 50 construction sites and carrying out work according to plan. So far, all construction items have been inspected and accepted according to the project's technical standards, ensuring quality and progress.
Currently, the runway foundation and M150-grade cement concrete structure have been completed to 62.2%, and the M350/45-grade cement concrete surface has been tested since early May 2024, with progress proceeding as planned.
Road Connection Project
Package 6.12 includes two connecting roads, T1 and T2. Road T1 connects to National Highway 51 (4.28 km long, 6 lanes), and Road T2 connects to the Ho Chi Minh City - Long Thanh - Dau Giay Expressway (about 3.5 km long, 4 lanes).
Currently, the construction consortium has completed 100% of the civil tunnels, cement-soil piles reached 74.9%, and earthworks completed 40-66%. For the bridges, pier foundations completed 81.2%, pier bodies completed 68.1%, pier caps completed 54.5%, and bored piles completed 86-94%.
Original image: cdn.tuoitre.vn
Overall Project Status
Currently, a total of 5,430 officials, engineers, and workers, along with 1,496 pieces of machinery and equipment, are involved in the construction of Phase 1 of the Long Thanh Airport project (packages 5.10, 4.6, and 6.12). From endless rubber forests to today's large construction site, after three and a half years of construction, Long Thanh Airport is being built at an accelerated pace.
According to the contractor's commitment, they will complete and put the runway into use by April 30, 2025, to celebrate the 50th anniversary of Vietnam's reunification, three months ahead of the contractual schedule.
The control tower, part of Phase 2 of the Long Thanh Airport project, started construction at the end of September 2023 and is currently 60 days ahead of schedule. The control tower is 123 meters high and is hailed as the 'brain' ensuring various airport operations.
➖➖➖➖➖➖➖➖➖➖
#FTT Real Estate Company Limited
(#Real Estate Consulting / #Leasing and Property Management & Sales / #Furniture and Decoration)
LINE Official Account @ymq0321f|Zalo +886 956 918 888|WeChat
┃Youtube: FTT REAL ESTATE
┃Website : www.fttland.com