Investing nearly 900 billion VND to build the Dau Tieng - Tan Phu Expressway
The first phase of the Dau Giay - Tan Phu Expressway construction project has just been approved, with a total length of over 60 kilometers and a total investment of nearly 900 billion VND. The project will be implemented under the Public-Private Partnership (PPP) model.
According to Decision No. 954/QD-BGTVT issued by the Minister of Transport, the project starts at kilometer 0, at the intersection with National Highway 1, belonging to the Ho Chi Minh City - Long Thanh - Dau Giay Expressway (Dau Giay Town, Thong Nhat District), and ends at kilometer 60+243.83, at the intersection with National Highway 20 connecting to the Tan Phu - Bao Loc Expressway project (Phu Trung Commune, Tan Phu District). The entire length of the project is located within Dong Nai Province.
In the first phase, the Dau Giay - Tan Phu Expressway will be built according to Grade 100 expressway standards, with a design speed of 100 km/h, a scale of four lanes, and a roadbed width of 17 meters. Bridges within soft soil foundation treatment areas, high embankment sections, interchange zones, and on the expressway will be designed according to the cross-section scale of the completion phase, with a roadbed width of 24.75 meters.
The entire route will have 5 interchanges, of which 4 interchanges will be invested in the first phase, and 1 interchange is planned. Specifically, they include: the Dau Giay interchange at kilometer 0, connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway and National Highway 1; the Provincial Road 763 interchange at kilometer 16+500, connecting the expressway with National Highway 20 and National Highway 1; the Gao Chang interchange at kilometer 38, connecting the expressway with National Highway 20, Dinh Quan District (Dong Nai Province), and Duc Linh District (Binh Thuan Province); the Tan Phu interchange at kilometer 57+700, connecting the expressway with National Highway 20 and the center of Tan Phu District. At the intersection with Provincial Road 770B at kilometer 10+400, a direct overpass will be temporarily invested, and the interchange will be completed at an appropriate time later.
Original image: media.vneconomy.vn
The project will build 26 bridges crossing roads; 4 ramp bridges crossing the expressway; 24 underground passages for residents; about 31 kilometers of collector-distributor roads, combined with underground passages for residents, bridges crossing roads, and existing roads, to ensure traffic connections and reduce impacts on residents' lives. For sections overlapping with existing roads, relocation roads will be built according to the current road scale. The project will also complete equipment systems on the expressway, ramps, traffic operation centers, management software, etc., to ensure smooth, safe, efficient, timely, convenient, and environmentally friendly expressway traffic.
The route is expected to have rest stops at the 40 km mark, with an area of about 3 hectares per side. The land acquisition costs for the rest stops are included in the total investment. The project covers a total area of about 378 hectares, of which Thong Nhat District accounts for about 95 hectares, Dinh Quan District about 156 hectares, Xuan Loc District about 5 hectares, and Tan Phu District about 122 hectares.
According to the approval decision, the total investment for the project is nearly 898.1 billion VND. Of this, the investor mobilizes about 768.1539 billion VND; state funding is about 130 billion VND, sourced from the 2021-2025 medium-term public investment plan and approved by the Prime Minister in Decision No. 1535/QĐ-TTg dated September 15, 2021. The funding allocation for 2025 is about 30%, for 2026 about 40%, and for 2027 about 30%. The project's calculated payback period is 18 years, 2 months, and 11 days.
The Vietnam Expressway Administration is the agency authorized by the Ministry of Transport to sign the contract; the Thang Long Project Management Board has been designated as the tendering entity. The method for selecting investors is domestic open bidding, with the investor selection period set for 2024-2025.
The approval decision also specifies a revenue increase-decrease sharing mechanism, which will be implemented in accordance with Article 82 of the Law on Public-Private Partnership Investment and the financial management mechanism for PPP projects as stipulated in Decree No. 28/2021/NĐ-CP dated March 26, 2021, by the Government.
The Dau Giay - Tan Phu Expressway construction and investment project was approved by the Prime Minister in Decision No. 1045/QĐ-TTg dated September 6, 2022, as part of the overall Dau Giay - Lien Khuong Expressway project, which connects Dong Nai Province and Da Lat (Lam Dong Province). It includes sub-projects: Dau Giay - Tan Phu, Tan Phu - Bao Loc, Bao Loc - Lien Khuong, and Lien Khuong - Prenn (Da Lat).
The project aims to meet transportation demand, reduce traffic pressure, and ensure traffic safety on National Highway 20; to complete and synchronously develop a high-capacity expressway along the Ho Chi Minh City - Dau Giay - Lien Khuong transport corridor, promoting the socio-economic development of Dong Nai Province, especially the Southeast region. The project will also foster cooperation and development between the Southeast region and the Mekong Delta, the Central Highlands, and the South Central region, enhance economic competitiveness, gradually complete the planned road network, and ensure national defense and security.