Overall report on the progress of the Long Thanh International Airport construction project
Overall Report on the Progress of the Long Thanh International Airport Construction Project
According to Announcement No. 306/TB-VPCP issued by the Government Office on July 9, 2024, Deputy Prime Minister Tran Hong Ha concluded at the working group meeting on the first phase of the Long Thanh International Airport construction investment project.
Project progress
The key Phase 2 and Phase 3 project components under the responsibility of Vietnam Air Traffic Management Corporation (VATM) and Airports Corporation of Vietnam (ACV)
are progressing on schedule or ahead of schedule according to the contract, and the Deputy Prime Minister expressed appreciation for the investor's efforts in ensuring project progress and quality.
However, some works in the first phase, managed by the Ministry of Agriculture and Rural Development, have not yet received funding support or had contractors selected. In particular, the progress of the fourth phase is very slow, and a feasible plan for selecting investors has not yet been developed, posing a risk of not being completed on schedule, which affects airport operations and leads to wasted investment costs.
Main Tasks
1. Land acquisition, compensation, support, and resettlement works:
Require the People's Committee of Dong Nai Province to complete land acquisition work by July 15, 2024, and hand over the remaining land area.
Direct the Southern Airports Authority to prepare land allocation documents and issue certificates of land use rights for the remaining land according to planning and functions.
2. Long Thanh International Airport Construction Investment Project Phase 1:
Phase 1 project (headquarters of state management agencies): The Ministry of Transport, together with the Ministry of Agriculture and Rural Development, the People's Committee of Dong Nai Province and related agencies, is working closely to urgently invest in the construction of health quarantine stations and animal and plant quarantine stations, investing in accordance with planning and functional requirements.
Phase 4 project (other works): Includes important works directly related to technical safety and operations, ensuring appropriate scale and functionality of the international airport. In particular, investment in the aircraft maintenance and repair center must meet international-standard technical, capacity and management requirements.
Solutions and recommendations
The Deputy Prime Minister instructed the Ministry of Transport to take charge of implementing Phase 4 of the project and to promptly report progress and feasible solutions to the Government. It is recommended to select capable and experienced international consultants to advise on the overall design and investor selection. The planning and investment departments should coordinate closely with the Ministry of Transport during the consultant selection and bidding document preparation process.
About the investor selection:
The bidding process was completed in July 2024.
Criteria for classifying investor operational efficiency suitable for the airport's scale and development level were established.
For investors providing aircraft maintenance and repair services:
Investors must have international investment experience, with priority given to capability, experience, and management standards.
For the following project components:
Cargo Terminal 2, Express Cargo Terminal, Cargo Receiving Warehouse (Logistics Area), Airport Hotel, Airport City: Investment projects reviewed and approved by the Ministry of Transport, and agreed upon with the State Capital Management Committee for ACV to lead the investment.
The Deputy Prime Minister requested the Ministry of Transport to promptly report the overall progress of the project to the Prime Minister, clarify the causes and responsibilities for the delay in implementing Phase 4, and propose feasible solutions.
ACV needs to designate capable and experienced staff to assist the Civil Aviation Authority of Vietnam in organizing the investor selection bidding, and to promptly receive and implement the Phase 4 content handed over by the Ministry of Transport.
The Deputy Prime Minister requested relevant agencies to diligently implement the directives, promptly deploy project components, ensure safety and quality, and complete them simultaneously to ensure the entire project can operate effectively.