Are GPU data centers really in short supply? Field verification in Vietnam and Taiwan
There is a claim online: pure CPU data centers have no future and sit empty; GPU data centers have a bright future, are fully leased, and are in short supply. FTT Land compared this claim against 35 public documents and verified it point by point. The conclusion is: the direction is right, but only half right. What is truly scarce in both places is not data center space, but "electricity."
Vietnam: Ho Chi Minh City's operational data center capacity is about 33MW, spread across 14 facilities, with a vacancy rate of 34.8% for leasable data center space, compared to the Asia-Pacific average of only 10.3% (Cushman & Wakefield H1 2026 report). FPT and GreenNode's H100s are both pay-as-you-go and available for immediate rental (about $2.34 to $2.54 per hour), with no reports of "can't rent" or "waiting lists." So "GPU data centers fully leased" does not currently hold true in Vietnam.
What is holding Vietnam back is electricity: the power company EVN requires new operators to build their own 110kV substations, reportedly costing between $8 million and $12 million each; whether data centers should use industrial or commercial electricity rates was still under dispute in 2026, with operators saying that switching to commercial rates would raise electricity bills by more than 50%. In terms of construction costs, Ho Chi Minh City and Hanoi average $5.7 million to $8.7 million per MW, with power systems accounting for 26% and land only 5%.
Taiwan: Since 2024, Taipower has stopped approving new data center electricity connections of 5MW or more north of Taoyuan. As of November 2025, there were 79 AI data center electricity applications totaling 4,758MW, with 40 approved totaling 3,033MW, but over 70% of approved capacity lapsed due to lack of construction within six months. Taipei's data center vacancy rate is under 3%, and Taiwan Mobile's 25MW data center in Guishan, Taoyuan was 100% sold out in pre-sales. So "GPU data centers fully leased" holds true in Taiwan, but "CPU data centers sitting empty" is not supported by data in either location.
Individual investors building and leasing: In a neutral scenario (50% occupancy) with 4 RTX5090s, payback is about 33 to 38 months; with 8 H100s in a neutral scenario, about 71 to 75 months. Only if occupancy stays at 70-80% or higher long-term can payback be achieved in 1 to 2 years, which is close to or exceeds the GPU generational cycle, so it's not recommended as an investment.
What this means for landlords: The part you can participate in during the AI wave is "industrial land and factories that can get electricity and fiber connections." Reports indicate that rents for data center land in Vietnam are 30% to 50% higher than for general industrial land. To find out if a piece of land can host an AI data center, first ask three things: how many MW of electricity can be obtained, how far is it from the substation, and whether there is dual-path fiber. FTT Land assists in evaluating power supply conditions for industrial land and factories in Ho Chi Minh City's Tan Phu Trung Industrial Park, Saigon Hi-Tech Park, and the former Binh Duong area.
Overseas real estate carries risks of exchange rate, regulatory and market changes; actual conditions are subject to the latest laws and individual case documents. Taiwan brokerage: 家澤不動產經紀有限公司 (FTT), broker: Chen Yi-chun (陳宜君), license no. (109) Jin Xian Zi No. 000057.