How Do You Inspect a Vietnam Off-Plan Apartment on Handover? Handover Checklist and Pink Book Processing Timeline (2026)

Before the handover of a Vietnam off-plan apartment, the developer must first complete acceptance inspection of the unit and the area's technical infrastructure; at handover, both parties must record both the contractual area and the measured area in the handover record. The developer must submit the application for the Pink Book within 50 days from the handover date, and the official processing time limit for the first issuance of the certificate is 3 working days.

Author: Yang Ping-Feng (Denny)Data as of 2026-11-25Legal provisions and figures checked word for word against the original text

A Vietnam off-plan apartment is not considered handed over just because the buyer "gets the keys." Under Vietnam's Law on Housing, the developer must first complete acceptance inspection of the unit itself and the technical infrastructure of its area before handing the unit over to the buyer; at handover, both parties must record both the "area stated in the contract" and the "measured area actually delivered" in the handover record, and this record is integral to the sale contract and cannot be viewed separately (Law on Housing, Article 37, Clause 4; Ministry of Construction Circular No. 05/2024/TT-BXD, attached Regulation on the Management and Use of Apartments, Article 5, Clause 2). The Pink Book (Certificate of Land Use Rights and Ownership of Houses, commonly known as the certificate) is a separate process: the developer must submit the application within 50 days from the handover date (Law on Real Estate Business, Article 17, Clause 3), while the processing time limit at the back end is set out separately (Appendix to Decree No. 151/2025/NĐ-CP).

This article only covers what to inspect on handover day, what documents to obtain, and how long to wait for the Pink Book; for payment milestones and the construction material grades of individual projects, please refer to your sale contract and property disclosure statement.

Key Points

QuestionConclusionBasis
When can the house be handed over?The house can only be handed over after the developer has completed acceptance of the house and the area's technical infrastructure; when handing over a bare-shell house, all exterior wall surfaces must be completedClause 4, Article 37 of the Housing Law
How is the area recorded at handover?Both the contract area and the actual delivered area must be written into the handover record or a contract appendix, and that record is deemed part of the contractClause 2, Article 5 of the Apartment Management and Use Regulations
How is the apartment area calculated?It is calculated by "clear dimensions", including interior partition walls, balconies and terraces, excluding exterior walls, party walls between units, interior columns and pipe boxesClause 1, Article 5 of the Apartment Management and Use Regulations
Which documents must be obtained at handover?As-built drawings of the building, equipment origin and installation contracts, wastewater treatment acceptance, operation and maintenance procedures, completion acceptance notice, parking area layout plan, etc.Clause 3, Article 10 of the Apartment Management and Use Regulations
When does the developer submit the application for the Pink BookSubmit within 50 days from the handover date (or from the date the buyer pays in full)Clause 3, Article 17 of the Law on Real Estate Business; Clause 8, Article 39 of the Law on Housing
How long after submission is the ownership certificate obtainedThe current maximum is 17 working days for first-time registration and 3 working days for first-time issuance of the ownership certificatePoint 1, Section II of the Appendix to Decree No. 151/2025/NĐ-CP
How much is the maintenance fundApartment buyers pay an additional maintenance fund of 2% of the property price, calculated separately from the property price and stated in the contractClause 1, Article 152 of the Law on Housing

Legal prerequisite for handover: acceptance inspection must be completed first

The Law on Housing sets a precondition for handover: the house cannot be handed over simply after the contract is signed and payment is made; the developer must first complete the acceptance inspection of the house and the surrounding infrastructure. The original text of Clause 4, Article 37:

Việc bàn giao nhà ở cho người mua, thuê mua chỉ được thực hiện sau khi đã hoàn thành việc nghiệm thu công trình nhà ở theo thiết kế đã được phê duyệt và nghiệm thu công trình hạ tầng kỹ thuật của khu vực có nhà ở được đầu tư xây dựng theo tiến độ của dự án đã được phê duyệt.

In plain terms: the house may be handed over to the buyer or lessee only after the house itself has passed acceptance inspection as completed in accordance with the approved design, and the technical infrastructure in the area where the house is located has also passed acceptance inspection as completed in accordance with the approved progress. The same clause also provides that if the project, under its investment policy, must build social infrastructure (schools, healthcare facilities, etc.), these facilities must also be completed and accepted before handover; when handing over a bare-shell house, all exterior wall surfaces of the house must be fully completed.

The same final paragraph also contains a provision specifically for apartments:

Khi bàn giao nhà chung cư, chủ đầu tư dự án đầu tư xây dựng nhà ở phải có đủ hồ sơ bàn giao nhà ở theo quy định của Chính phủ.

Plain language: When handing over an apartment, the developer must have all the handover documents required by government regulations ready. In other words, "incomplete documents" is legally a valid reason to refuse handover—it is not just about inspecting the condition of the unit.

What to inspect on handover day: three lines—area, equipment, documents

1. Area: both the contractual area and the measured area must be written in

Original text of Clause 2, Article 5 of the "Regulations on the Management and Use of Apartments":

Khi bàn giao căn hộ, các bên phải ghi rõ diện tích sử dụng căn hộ thực tế bàn giao và diện tích ghi trong hợp đồng mua bán, thuê mua căn hộ đã ký vào trong biên bản bàn giao căn hộ hoặc phụ lục hợp đồng; biên bản bàn giao căn hộ hoặc phụ lục hợp đồng được coi là một bộ phận không thể tách rời của hợp đồng mua bán, thuê mua căn hộ.

Plain language: At handover, both parties must write both the "actually delivered usable area" and the "area recorded in the signed contract" into the handover record or contract appendix; this record or appendix is regarded as integral to the sale contract and cannot be treated separately. In practice, this is the most critical written basis for future area disputes, so before signing, make sure both figures appear on it.

How area is calculated is also expressly provided. Clause 1, Article 5 (original text) provides:

Diện tích sử dụng căn hộ được tính theo kích thước thông thủy như ví dụ theo hình vẽ dưới đây và được ghi vào giấy tờ chứng nhận về quyền sử dụng đất, quyền sở hữu nhà ở gắn liền với đất (sau đây gọi chung là Giấy chứng nhận) cấp cho người mua, thuê mua, bao gồm cả phần diện tích tường ngăn các phòng bên trong căn hộ và diện tích ban công, lô gia (nếu có) gắn liền với căn hộ đó, không tính diện tích tường bao căn hộ, tường phân chia các căn hộ, diện tích sàn có cột, hộp kỹ thuật và tường bao hộp kỹ thuật (nếu có) nằm bên trong căn hộ.

Plain language: Apartment usable area is calculated on a "clear space" (thông thủy) basis and is written into the ownership certificate issued to the buyer; it includes interior room partition walls and attached balconies and terraces, but excludes exterior walls, partition walls between units, the floor area of interior columns, pipe boxes and their enclosing walls. So the same unit will naturally have different figures when the advertisement uses a "including common areas" method and the ownership certificate uses the clear-space method; what must be compared at handover is whether "what the contract states" and "what the handover record states" use the same calculation method.

2. Equipment and maintenance fund: the 2% is calculated separately

Original text of Clause 1, Article 152 of the "Housing Law":

Đối với căn hộ, phần diện tích khác trong nhà chung cư mà chủ đầu tư dự án đầu tư xây dựng nhà ở bán, cho thuê mua thì người mua, thuê mua phải đóng kinh phí bảo trì là 2% giá trị căn hộ, phần diện tích bán, cho thuê mua này; khoản tiền này được tính riêng với tiền bán, tiền thuê mua căn hộ, phần diện tích khác trong nhà chung cư và được quy định rõ trong hợp đồng mua bán, hợp đồng thuê mua.

Plain language: For apartments sold or sold under a lease-purchase (thuê mua) arrangement by the developer, the buyer must pay a maintenance fund of 2% of the housing price; this amount is calculated separately from the housing price and must be stated in the sale contract. At handover settlement, this is an amount independent of and in addition to the housing price—not a miscellaneous fee included in the total price.

(FTT suggestion: Prepare an "equipment list" on handover day, check item by item whether the air conditioners, kitchen units, bathroom fixtures, intercom, and electricity and water meter numbers match the contract appendices, and take photos for records; the statutory provisions cover documents and area, while equipment details mainly depend on what the contract appendices stipulate.)

3. Documents: Building-level information is handed over separately

In addition to the handover record for one's own unit, Article 10, Clause 3 of the "Apartment Management and Use Regulations" also stipulates that within 20 days after a written request by the Management Committee (or the resident representative in the absence of a Management Committee), the developer must deliver two certified copies of the building documents, including:

  • As-built drawings and building layout plans (with a schedule of drawings and descriptions);
  • Source documents and installation contracts for building equipment;
  • Completion acceptance documents for the wastewater treatment system;
  • Operation, development, and maintenance procedures;
  • The approval notice of the completion acceptance result from the construction authority;
  • Parking area floor plan indicating resident parking spaces and public parking spaces.

Original text (first part of Article 10, Clause 3):

Trong thời hạn 20 ngày, kể từ ngày Ban quản trị hoặc người đại diện quản lý nhà chung cư (đối với trường hợp không phải thành lập Ban quản trị) có văn bản yêu cầu chủ đầu tư bàn giao hồ sơ nhà chung cư thì chủ đầu tư có trách nhiệm bàn giao 02 bộ hồ sơ sao y từ bản chính cho Ban quản trị.

Plain language: Within 20 days from the written request of the Management Committee (or resident representative), the developer must deliver two certified copies of the originals to the Management Committee. The 20 days in this clause apply to building-level documents, not to individual unit handovers.

Pink Book: submission within 50 days, after which comes the government processing time

After handover, the most frequently asked question is "when will the title certificate be issued." This needs to be looked at in two stages.

The first paragraph concerns the developer's submission obligation. Clause 3, Article 17 of the Law on Real Estate Business original text:

Trong thời hạn 50 ngày kể từ ngày bàn giao nhà ở cho bên mua hoặc kể từ thời điểm bên thuê mua nhà ở đã thanh toán đủ tiền theo thỏa thuận thì phải nộp hồ sơ đề nghị cơ quan nhà nước có thẩm quyền cấp giấy chứng nhận về quyền sử dụng đất, quyền sở hữu tài sản gắn liền với đất theo quy định của pháp luật về đất đai cho bên mua, thuê mua, trừ trường hợp bên mua, thuê mua tự nguyện làm thủ tục cấp giấy chứng nhận.

In plain terms: within 50 days from the handover date, or from the date the purchaser-lessee (thuê mua) fully pays the amount under the contract, the developer must submit an application to the competent authority to obtain the certificate of land use rights and house ownership for the buyer or purchaser-lessee; unless the buyer voluntarily handles it themselves. The same 50-day obligation is also set out in Clause 8, Article 39 of the Law on Housing, and the two laws correspond to each other on the same deadline.

The second paragraph concerns the government-side processing time limit. This part has been revised once, and the current version must be used:

  • Article 22 of the former Decree No. 101/2024/NĐ-CP once prescribed the issuance time limit, but that article was repealed by Point b, Clause 4, Article 21 of Decree No. 151/2025/NĐ-CP (that decree took effect on 2025-07-01 and applies until before 2027-03-01).
  • The current time limit is in Point 1, Section II of the Appendix to Decree No. 151/2025/NĐ-CP:

Đăng ký đất đai, tài sản gắn liền với đất lần đầu là không quá 17 ngày làm việc; cấp Giấy chứng nhận quyền sử dụng đất, quyền sở hữu tài sản gắn liền với đất lần đầu là không quá 03 ngày làm việc.

In plain terms: first-time land registration shall not exceed 17 working days; first-time issuance of the certificate shall not exceed 3 working days. Note that this is the upper limit for "agency processing" and does not include the time for the developer to supplement documents or pay taxes and fees; in practice, the period from submission to receiving the certificate is usually longer than 20 working days.

(FTT suggestion: around the 45th day after handover, ask the developer for the submission receipt or case number; if it has not been submitted after 50 days, send a written reminder; this is an operational suggestion, as the provisions only set the 50-day submission obligation and do not prescribe a format for the reminder.)

Recommended inspection order on the handover day

(The following order is FTT's operational suggestion; the provisions only specify "what to inspect and what to record" and do not prescribe an inspection order.)

  1. Check the documents first, then the condition of the unit. Confirm that the handover record contains both the contract area and the measured area figures, and obtain copies of the building documents listed in Clause 3, Article 10.
  2. Check the equipment and meter numbers. Match the water meter, electricity meter, intercom, and air-conditioner models one by one against the contract annex, and take photos.
  3. Confirm the calculation basis for the 2% maintenance fund. Confirm the calculation base stated in the contract and obtain the payment receipt.
  4. Record defects and set a deadline for a written response. Write property defects into the handover record; do not report them only verbally.
  5. Ask clearly about the submission timeline. Ask the developer to state the expected submission date in writing, and keep the contact details of the liaison.

Frequently Asked Questions

For off-plan apartment handover in Vietnam, must acceptance inspection be completed first?

Yes. Under Article 37, Clause 4 of the Law on Housing, the developer must first complete acceptance inspection of the housing itself according to the approved design, and acceptance inspection of the technical infrastructure in the area where the housing is located according to the approved progress, before handover; when handing over a rough-built house, all exterior wall surfaces must be completed. When handing over an apartment, the handover documents required by the government must also be fully prepared.

What if the area stated in the handover record differs from the area in the contract?

Both should be recorded at the same time. Article 5, Clause 2 of the Regulations on Management and Use of Apartments requires that at handover, both the "actual delivered usable area" and the "area stated in the contract" be written into the handover record or a contract appendix; that document is regarded as integral to the contract and cannot be treated separately; how the difference is handled depends on the contract terms, so confirm both figures are present before signing.

How long does the developer have to submit the documents for the Pink Book?

Under Article 17, Clause 3 of the Law on Real Estate Business and Article 39, Clause 8 of the Law on Housing, submission must be made within 50 days from the handover date (for hire-purchase buyers, the date the payment is fully settled), unless the buyer voluntarily handles it themselves. For the agency processing time limits after submission, current regulations are no more than 17 working days for first-time registration and no more than 3 working days for first-time issuance of the certificate (Appendix to Decree No. 151/2025/NĐ-CP).

Is the 2% maintenance fund included in the apartment price?

No. Under Article 152, Clause 1 of the Law on Housing, apartment buyers must pay a maintenance fund of 2% of the apartment price; this amount is calculated separately from the apartment price and must be stated in the sale contract.

Related Articles

Sources

  1. Consolidated Law on Housing of Vietnam No. 79/VBHN-VPQH (consolidating 27/2023/QH15 and subsequent amending laws), Official Gazette Issue 204, 2026-04-10, https://congbaocdn.chinhphu.vn/180507251028987904/2026/4/10/469209-1775794482_v1_1775811756_signed.pdf (citing Articles 37, 39 and 152)
  2. Consolidated Law on Real Estate Business of Vietnam No. 06/VBHN-VPQH (consolidated by the National Assembly Office on 2025-02-21), Official Gazette Issues 493+494, 2025-03-16, https://congbao.chinhphu.vn/van-ban/van-ban-hop-nhat-so-06-vbhn-vpqh-44399.htm (citing Article 17, Clause 3)
  3. Ministry of Construction Circular No. 05/2024/TT-BXD (signed 2024-07-31, effective 2024-08-01), Official Gazette issues 927+928 and 929+930, 2024-08-14, https://congbao.chinhphu.vn/van-ban/thong-tu-so-05-2024-tt-bxd-42480.htm (with Articles 5 and 10 of the Regulations on Apartment Management and Use)
  4. Government Decree No. 151/2025/NĐ-CP (effective 2025-07-01, in force until before 2027-03-01), Official Gazette issues 829+830, 831+832, 833+834, 2025-06-24, https://congbao.chinhphu.vn/van-ban/nghi-dinh-so-151-2025-nd-cp-45191.htm (Article 21, Clause 4; Appendix Section II)
  5. Government Decree No. 101/2024/NĐ-CP (land registration and first issuance of certificates), Official Gazette issues 913+914, https://congbao.chinhphu.vn/van-ban/nghi-dinh-so-101-2024-nd-cp-42434.htm (for version tracing only; Article 22 was repealed by the Decree in item 4)
Feng
Yang Ping-Feng (Denny)
Consultant at FTT Land. Serving both Taiwan and Ho Chi Minh City.
Ask a consultant on LINE

Author: Denny (楊秉豐)|Advisor, FTT Land
Signing broker for this advertisement: 陳宜君 (broker license no. (109)金縣字第000057號)
Brokerage: 家澤不動產經紀有限公司 (Taiwan brokerage)

Overseas real estate investment carries risks. Investors are advised to read the marketing materials carefully and consider thoroughly before transacting.

This article is a compilation of legal and market information, not individual investment advice; case-specific conditions are subject to the property description and the sale and purchase contract. Data as of 2026-11-25.
This article was written and reviewed by the FTT advisory team; some data compilation was assisted by AI tools.

Related videos

  • 1:29

    Can foreigners permanently own property in Vietnam? | Current regulations under the 2024 new law

  • 1:14

    Taiwanese buying property in Vietnam | Current regulations after the 2024 new law

LINE Free Consultation Add Zalo Friend WeChat

Add Zalo Friend

Zalo QR Code Binh Phong +886 956 918 888

Binh Phong

+886 956 918 888

Scan the QR Code with Zalo, or search for the phone number above in Zalo to add as a friend

Open Zalo directly on your phone

Add WeChat Friend

WeChat QR Code mr. phong 秉豐

mr. phong 秉豐

Open WeChat → “Scan” to scan the QR Code and add as a friend; on mobile, you can take a screenshot first, then select it from the album in WeChat's Scan function